elektroenergetika
POWER SYSTEMS

NEWS

EVENTS
BOOKS

BLOG
UNIVERSITIES

NIKOLA TESLA
LINKS

CONTACT
elektroenergetika POWER

SYSTEMS
NEWS EEE EEE NEXT >

Apr 30, 2026 - How Does Italy Balance Agriculture and Solar Energy in Agrivoltaic Projects?

Apr 29, 2026 - Oil Chaos Is Triggering an EV Boom!

Apr 28, 2026 - Solar Saturation & Grid Collapse: Spain`s BESS Opportunity

Apr 26, 2026 - Why Electric Trucks matter MORE than Electric Cars!

Apr 25, 2026 - Fusion reactors now work, but how close are they to rollout?

Apr 24, 2026 - Two Harvests. One Field. California`s Smarter Solar: Agrivoltaics

Apr 24, 2026 - China`s solar exports double in a month to hit record highs

Web Analytics
Trending Now: Solar, Wind, Grid

Feb 2, 2026 - Darlington nuclear power station set to reopen ahead of schedule



Ontario`s energy minister says the Ford government is seeing through its future plans on nuclear energy.
Stephen Lecce announced Monday that refurbishment work at the Darlington Power Plant near Oshawa is complete and just about ready for service.
Lecce says the entire $12.8 billion project is four months ahead of schedule and $150 million under budget as well.
However, Ontario`s green party believes the province`s all-in approach on nuclear, won`t make energy more affordable for Ontarians.
“We have the opportunity to be an energy superpower on the global stage and people look for expertise of our people here in Ontario,” said Ontario Labour Minister David Piccini.
Ontario`s plans for expanding its nuclear power capabilities appear to be on track after the province says the revitalization of the Darlington power plant is complete and built-to-last until 2055.
“Darlington`s unit 4 construction is complete and returning to service, four months ahead of schedule, with the full Darlington refurbishment $150 million under budget,” said Lecce.